Oregon · Senate Bill 6 · 2025 Regular Session

Requires the Department of Consumer and Business Services, a municipality, a building official or any other agency or official responsible for…

  1. Introduced Mar 10, 2025
  2. In committee Mar 11, 2025
  3. Died  
  4. Passed the House  
  5. To the governor  
  6. Became law  

What it does

The legislature's own summary of the bill, or its official long title.

Says an application for a building permit must be acted on not later than 45 days after it is done. (Flesch Readability Score: 63.8). Requires the Department of Consumer and Business Services, a municipality, a building official or any other agency or official responsible for administering and enforcing the state building code to approve and issue, or disapprove and deny, any application for a building permit for…

Read the full title (224 words)

Says an application for a building permit must be acted on not later than 45 days after it is done. (Flesch Readability Score: 63.8). Requires the Department of Consumer and Business Services, a municipality, a building official or any other agency or official responsible for administering and enforcing the state building code to approve and issue, or disapprove and deny, any application for a building permit for middle housing or conventional single-family residential housing in a residential subdivision with more than six lots not later than 45 business days after the date on which the applicant submits a complete application. Requires any other agency or jurisdiction that must review an application for a building permit to complete the review within 10 business days after receipt or the portion of the application that is subject to the review is approved. Declares that an application for a building permit is approved if the department, a municipality, a building official or any other agency or official fails to deny or act upon the application within the allowable period. Requires prompt issuance of the building permit in such circumstances. Makes the department, municipality, building official or other agency or official that fails to promptly issue the building permit liable to the applicant for the fees the applicant paid and the costs the applicant incurred in preparing the application.

Read the full official title (76 words)

Requires the Department of Consumer and Business Services, a municipality, a building official or any other agency or official responsible for administering and enforcing the state building code to approve and issue, or disapprove and deny, any application for a building permit for middle housing or conventional single-family residential housing in a residential subdivision with more than six lots not later than 45 business days after the date on which the applicant submits a complete application.

Every action

7 steps, oldest first, as the legislature records them.

  1. SenateIntroduction and first reading. Referred to President's desk.
  2. CommitteeReferred to Housing and Development. · Senate Housing and Development
  3. CommitteePublic Hearing held. · Senate Housing and Development
  4. CommitteeWork Session held. · Senate Housing and Development
  5. CommitteeRecommendation: Do pass with amendments and be referred to Ways and Means. (Printed A-Eng.) · Senate Housing and Development
  6. CommitteeReferred to Ways and Means by order of the President. · Joint Ways and Means
  7. SenateIn committee upon adjournment.

Roll calls

1 recorded vote: 0 on the floor, 1 in committee. Each shows how every member voted.

Committee votes

DateWhereQuestionResult
Apr 7, 2025 Senate Housing and Development Recommendation: Do pass with amendments and be referred to Ways and Means. (Printed A-Eng.)
Members

Yes · 5

5–0

Sponsors

The member who introduced it, joined by 1 cosponsor: 1 Republican.

All 1 cosponsor

From Oregon's official records (api.oregonlegislature.gov), checked Nov 13, 2026. Text links go to the official versions; LegiList does not copy bill text.