S 2083 · 114th Congress 2015โ€“2017, ended

A bill to extend the deadline for commencement of construction of a hydroelectric project.

Latest action · Dec 16, 2015 Placed on Senate Legislative Calendar under General Orders. Calendar No. 337.

Progress

Where this bill reached, and when. A stage with no date was not reached; one that failed a vote and later carried shows the date it carried.

  1. IntroducedSep 28, 2015
  2. Passed SenateNot reached
  3. Passed HouseNot reached
  4. To the PresidentNot reached
  5. Became lawNot reached

Summary

(This measure has not been amended since it was introduced. The summary has been expanded because action occurred on the measure.)

(Sec. 1) This bill permits the Federal Energy Regulatory Commission (FERC), upon licensee request, to extend for up to three consecutive two-year periods from the expiration date of the extension originally issued by FERC the time period during which the licensee must commence construction of project numbered 12642.

FERC may also reinstate the license effective as of its expiration date if the period required for commencement of project construction has expired before enactment of this Act. The first extension authorized under this Act shall take effect upon that expiration date.

Cosponsors 1

Members who signed on, in the order they did. All signed on Sep 28, 2015.

SeatCosponsorSigned on
R-NCThom TillisOriginalSep 28, 2015

Committees 1

Where it was sent and what each committee and subcommittee did with it, in order.

ChamberCommitteeWhat it did
SenateEnergy and Natural Resources Committee
Referred Sep 28, 2015Hearings Oct 8, 2015Markup Nov 19, 2015Reported Dec 16, 2015

Actions 6

Everything that happened, newest first.

  1. Dec 16, 2015Committee on Energy and Natural Resources. Reported by Senator Murkowski without amendment. With written report No. 114-192.
  2. Dec 16, 2015Placed on Senate Legislative Calendar under General Orders. Calendar No. 337.
  3. Nov 19, 2015Committee on Energy and Natural Resources. Ordered to be reported without amendment favorably.
  4. Oct 8, 2015Committee on Energy and Natural Resources. Hearings held. Hearings printed: S.Hrg. 114-381.
  5. Sep 28, 2015Introduced in Senate

Research

What has been written about this bill: committee reports, cost estimates, the sponsor’s authority statement, printed hearings and the Congressional Research Service’s work.

Committee report

Congressional Budget Office cost estimate

  1. Dec 10, 2015S. 2083, a bill to extend the deadline for commencement of construction of a hydroelectric projectAs ordered reported by the Senate Committee on Energy and Natural Resources on November 19, 2015

Printed hearings 1

Hearings whose printed record names this bill, newest first: hearings on it, and wider hearings where it came up.

NumberHearingCommitteeHeld
S. Hrg. 114-381WESTERN AND ALASKA WATER LEGISLATION489 pagesEnergy and Natural Resources CommitteeOct 8, 2015

Related bills 6

Companion bills and other measures the record links to this one.

Titles 1

Every title it has carried, official and short, at each stage.

Official Title as Introduced
A bill to extend the deadline for commencement of construction of a hydroelectric project.

Subjects

Assigned by the Library of Congress. Policy area: Energy.

Text 2

Each version as it was printed, newest first.

  1. Dec 16, 2015Reported to Senate
  2. Sep 28, 2015Introduced in Senate

Support LegiList

This page is free, carries no paywall, and is built and maintained by one person. If the record here is useful to you, a few dollars keeps it going.

Processed by Stripe in a separate window. LegiList never sees card details.

Everything here is as published by Congress: the summary is the Congressional Research Service's, the action wording is the clerks', and the subjects are the Library of Congress's. How far it got is read from the actions themselves, taking the most recent one of each kind, so a bill that failed a vote and later passed is shown as having passed. Records come from this bill on Congress.gov and govinfo.gov; cost estimates are the Congressional Budget Office's, and the hearings are the printed hearings GovInfo publishes, which can appear months after the hearing.