State Corporation Commission; time frame for completion of certain proceedings.
State Corporation Commission; time frame for completion of certain proceedings. Requires the State Corporation Commission to complete proceedings involving an application for a certificate, permit, or approval required for the construction or operation by a public utility of a small renewable energy project or certain transmission lines within 180 days following such application. The bill permits the Commission, for good cause shown, to grant a one-time extension of 30 additional days after such 180-day period has elapsed.
| Date | Event | Detail |
|---|---|---|
| 2026-01-12 | Introduced | Bill introduced |
| 2026-04-06 | Status | enacted |
| 2026-04-06 | Latest Action | Acts of Assembly Chapter text (CHAP0148) |