Virginia · Senate Bill 1049 · 2025 Regular Session

Electric utilities; approval required for construction of certain electrical transmission lines.

  1. Introduced Jan 7, 2025
  2. In committee Jan 7, 2025
  3. Failed  
  4. Passed the House of Delegates  
  5. To the governor  
  6. Became law  

What it does

The legislature's own summary of the bill, or its official long title.

Electric utilities; approval required for construction of certain electrical transmission lines. Prohibits the construction of a new transmission line overhead unless the State Corporation Commission first determines that the construction of such transmission line in whole or in part underground is not in the public interest.

Every action

4 steps, oldest first, as the legislature records them.

  1. SenatePrefiled and ordered printed; Offered 01-08-2025 25104110D
  2. CommitteeReferred to Committee on Commerce and Labor · Senate Commerce and Labor
  3. SenateFiscal Impact Statement from State Corporation Commission (SB1049)
  4. CommitteeFailed to report (defeated) in Commerce and Labor (4-Y 11-N) · Senate Commerce and Labor4–11 vote

Roll calls

1 recorded vote: 0 on the floor, 1 in committee. Each shows how every member voted.

Committee votes

DateWhereQuestionResult
Jan 27, 2025 Senate Commerce and Labor Failed to report (defeated) in Commerce and Labor (4-Y 11-N)
Members

Yes · 4

No · 11

Failed 4–11

Sponsors

The member who introduced it.