The legislature's own summary of the bill, or its official long title.
Authorizing the construction, permitting, and operation of energy generating systems that produce energy from natural gas until the State meets 100% of its energy needs from renewable energy resources, including nuclear energy; establishing certain requirements for energy generating systems that produce energy from natural gas; requiring the Department of the Environment to approve or deny an application for the construction of a new energy generating system that produces energy from natural gas; etc.
Every action
5 steps, oldest first, as the legislature records them.
- House of DelegatesPre-filed
- CommitteeFirst Reading Economic Matters · House of Delegates Economic Matters Committee
- House of DelegatesHearing 1/23 at 1:00 p.m.
- House of DelegatesHearing canceled
- House of DelegatesWithdrawn by Sponsor
Roll calls
1 recorded vote: 0 on the floor, 1 in committee. Each shows how every member voted.
Committee votes
| Date | Where | Question | Result |
|---|---|---|---|
| Feb 7, 2025 | House of Delegates Economic Matters Committee | WDR MembersYes · 21
|
21–0 |
Sponsors
The member who introduced it.
-
Nino MangioneR Primary sponsor · District 42A