Indiana · House Bill 1007 · 124th General Assembly, First Regular Session

Energy generation resources.

  1. Introduced Jan 13, 2025
  2. In committee Jan 13, 2025
  3. Passed the House Feb 13, 2025
  4. Passed the Senate Apr 15, 2025
  5. To the governor  
  6. Became law May 6, 2025

What it does

The legislature's own summary of the bill, or its official long title.

Provides a credit against state tax liability for expenses incurred in the manufacture of a small modular nuclear reactor (SMR) in Indiana. Establishes procedures under which certain energy utilities may request approval for one or more of the following from the Indiana utility regulatory commission (IURC): (1) An expedited generation resource plan (EGR plan) to meet customer load growth that exceeds a specified…

Read the full title (821 words)

Provides a credit against state tax liability for expenses incurred in the manufacture of a small modular nuclear reactor (SMR) in Indiana. Establishes procedures under which certain energy utilities may request approval for one or more of the following from the Indiana utility regulatory commission (IURC): (1) An expedited generation resource plan (EGR plan) to meet customer load growth that exceeds a specified threshold. (2) A generation resource submittal for the acquisition of a specific generation resource in accordance with an approved EGR plan. (3) A project to serve one or more large load customers. Sets forth: (1) the requirements for approval of each of these types of requests; (2) standards for financial assurances by large load customers; and (3) cost recovery mechanisms for certain acquisition costs or project costs incurred by energy utilities. Amends the statute concerning public utilities' annual electric resource planning reports to the IURC to provide that for an annual report submitted after December 31, 2025, a public utility must include information as to the amount of generating resource capacity or energy that the public utility plans to retire or refuel with respect to any electric generation resource of at least 125 megawatts. Provides that for any planned retirement or refueling, the public utility must include, along with other specified information, information as to the public utility's plans with respect to the following: (1) For a retirement, the amount of replacement capacity identified to provide approximately the same accredited capacity within the appropriate regional transmission organization (RTO) as the capacity of the facility to be retired. (2) For a refueling, the extent to which the refueling will maintain or increase the current generating resource accredited capacity or energy that the electric generating facility provides, so as to provide approximately the same accredited capacity within the appropriate RTO. Requires IURC staff to prepare a staff report for each public utility report that includes a planned electric generation resource retirement. Provides that if, after reviewing a public utility's report and any related staff report, the IURC is not satisfied that the public utility can satisfy both its planning reserve margin requirement and the statute's prescribed reliability adequacy metrics, the IURC shall conduct an investigation into the reasons for the public utility's inability to meet these requirements. Provides that if the public utility's report indicates that the public utility plans to retire an electric generating facility within one year of the date of the report, the IURC must conduct such an investigation. Provides that: (1) a public utility may request, not earlier than three years before the planned retirement date of an electric generation facility, that the IURC conduct an investigation into the planned retirement; and (2) if the IURC conducts an investigation at the request of the public utility within that three year period, the IURC may not conduct a subsequent investigation that would otherwise be required under the bill's provisions unless the IURC is not satisfied that the public utility can satisfy both its planning reserve margin requirement and the statutory reliability adequacy metrics as of the time the investigation would otherwise be required. Provides that if a CPCN is granted by the IURC for a facility intended to repower or replace a generation unit that is planned for retirement, and the CPCN includes findings that the project will result in at least equivalent accredited capacity and will provide economic benefit to ratepayers as compared to the continued operation of the generating unit to be retired, the CPCN constitutes approval by the IURC for purposes of an investigation that would otherwise be required. Provides that if, after an investigation, the IURC determines that the capacity resources available to the public utility will not be adequate to allow the public utility to satisfy both its planning reserve margin requirements and the statute's prescribed reliability adequacy metrics, the IURC shall issue an order: (1) directing the public utility to acquire or construct; or (2) prohibiting the retirement or refueling of; such capacity resources that are reasonable and necessary to enable the public utility to meet these requirements. Provides that if the IURC does not issue an order in an investigation within 120 days after the initiation of the investigation, the public utility is considered to be able to satisfy both its planning reserve margin requirement and the statutory reliability adequacy metrics with respect to the retirement of the facility under investigation. Provides that if the IURC issues an order to prohibit the retirement or refueling of an electric generation resource, the IURC shall create a sub-docket to authorize the public utility to recover in rates the costs of the continued operation of the electric generation resource proposed to be retired or refueled, subject to a finding by the IURC that the continued costs of operation are just and reasonable. Makes a technical change to another Indiana Code section to recognize the redesignation of subsections within the section containing these provisions.

Every action

35 steps, oldest first, as the legislature records them.

Show the 27 earlier steps
  1. HouseAuthored by Representative Soliday
  2. HouseCoauthored by Representatives Shonkwiler and Pressel
  3. CommitteeFirst reading: referred to Committee on Utilities, Energy and Telecommunications · House Utilities, Energy and Telecommunications
  4. HouseRepresentative Bartels added as coauthor
  5. CommitteeCommittee report: amend do pass, adopted · House Ways and Means
  6. CommitteeRecommitted to Committee on Ways and Means pursuant to House Rule 126.3 · House Ways and Means
  7. HouseCommittee report: do pass, adopted
  8. HouseSecond reading: amended, ordered engrossed
  9. HouseAmendment #1 (Pierce M) failed; Roll Call 106: yeas 26, nays 6926–69 vote
  10. HouseAmendment #2 (Pierce M) prevailed; voice vote
  11. HouseAmendment #3 (Pierce M) failed; Roll Call 107: yeas 27, nays 6727–67 vote
  12. HouseThird reading: passed; Roll Call 152: yeas 68, nays 2568–25 vote
  13. HouseSenate sponsor: Senator Koch
  14. HouseRule 104.1 suspended
  15. HouseRepresentatives Lauer, Heaton, May, Lucas, Smith H, DeVon, Karickhoff, Heine, Smaltz, Teshka, Snow, Jordan, Thompson, Steuerwald, Olthoff, Zimmerman, Haggard, Aylesworth, Miller D, Commons, Judy, Hall, Lehman, Prescott, Culp, Borders, Baird, Wesco, Lopez, Carbaugh, McNamara, Jeter, Abbott added as coauthors
  16. HouseReferred to the Senate
  17. CommitteeFirst reading: referred to Committee on Utilities · Senate Utilities
  18. CommitteeCommittee report: amend do pass adopted; reassigned to Committee on Tax and Fiscal Policy · Senate Tax and Fiscal Policy
  19. SenateCommittee report: do pass, adopted
  20. SenateSenator Rogers added as cosponsor
  21. SenateSecond reading: amended, ordered engrossed
  22. SenateAmendment #6 (Koch) prevailed; voice vote
  23. SenateAmendment #5 (Yoder) failed; Roll Call 373: yeas 11, nays 3511–35 vote
  24. SenateAmendment #2 (Hunley) failed; voice vote
  25. SenateSenator Schmitt added as cosponsor
  26. SenateThird reading: passed; Roll Call 423: yeas 36, nays 1336–13 vote
  27. SenateSenator Niezgodski added as cosponsor
  1. SenateReturned to the House with amendments
  2. HouseMotion to concur filed
  3. HouseHouse concurred with Senate amendments; Roll Call 512: yeas 63, nays 2363–23 vote
  4. HouseSigned by the Speaker
  5. SenateSigned by the President Pro Tempore
  6. SenateSigned by the President of the Senate
  7. HouseSigned by the Governor
  8. HousePublic Law 217

Roll calls

12 recorded votes: 6 on the floor, 6 in committee. Each shows how every member voted.

Amendment #1 (Pierce M) failed; Roll Call 106: yeas 26, nays 69 · Full House

Failed 26–69
Feb 10, 2025 · journal entry
Yes 26 No 69 Not voting 5
Democrats: 26 yes, 1 no Republicans: 0 yes, 68 no
How each member voted

Yes · 26

No · 69

Not voting · 1

Excused · 4

Amendment #3 (Pierce M) failed; Roll Call 107: yeas 27, nays 67 · Full House

Failed 27–67
Feb 10, 2025 · journal entry
Yes 27 No 67 Not voting 6
Democrats: 27 yes, 0 no Republicans: 0 yes, 67 no
How each member voted

Yes · 27

No · 67

Not voting · 2

Excused · 4

Third reading: passed; Roll Call 152: yeas 68, nays 25 · Full House

Passed 68–25
Feb 13, 2025 · journal entry
Yes 68 No 25 Not voting 7
Democrats: 0 yes, 25 no Republicans: 68 yes, 0 no
How each member voted

Yes · 68

No · 25

Not voting · 3

Excused · 4

Amendment #5 (Yoder) failed; Roll Call 373: yeas 11, nays 35 · Full Senate

Failed 11–35
Apr 10, 2025 · journal entry
Yes 11 No 35 Not voting 4
Democrats: 10 yes, 0 no Republicans: 1 yes, 35 no
How each member voted

Yes · 11

No · 35

Not voting · 2

Excused · 2

Third reading: passed; Roll Call 423: yeas 36, nays 13 · Full Senate

Passed 36–13
Apr 15, 2025 · journal entry
Yes 36 No 13 Not voting 1
Democrats: 1 yes, 9 no Republicans: 35 yes, 4 no
How each member voted

Yes · 36

No · 13

Excused · 1

House concurred with Senate amendments; Roll Call 512: yeas 63, nays 23 · Full House

Passed 63–23
Apr 22, 2025 · journal entry
Yes 63 No 23 Not voting 14
Democrats: 3 yes, 22 no Republicans: 60 yes, 1 no
How each member voted

Yes · 63

No · 23

Excused · 14

Committee and other votes

DateWhereQuestionResult
Jan 21, 2025 House Utilities, Energy and Telecommunications House Committee on Utilities, Energy and Telecommunications: amendment #1 (Energy generation resources.)
Members

Yes · 8

No · 4

8–4
Jan 28, 2025 House Utilities, Energy and Telecommunications House Committee on Utilities, Energy and Telecommunications: Do pass amended
Members

Yes · 9

No · 4

9–4
Feb 5, 2025 House Ways and Means House Committee on Ways and Means: Do pass
Members

Yes · 16

No · 7

Excused · 1

16–7
Mar 27, 2025 Senate Utilities Senate Committee on Utilities: amendment #6 (Utility customer assistance programs.)
Members

Yes · 3

No · 8

3–8
Mar 27, 2025 Senate Utilities Senate Committee on Utilities: Do pass amended
Members

Yes · 8

No · 3

8–3
Apr 8, 2025 Senate Tax and Fiscal Policy Senate Committee on Tax and Fiscal Policy: Do pass
Members

Yes · 10

No · 3

10–3

Sponsors

The member who introduced it, joined by 39 cosponsors: 38 Republicans, 1 Democrat.

All 39 cosponsors

Support LegiList

This page is free, carries no paywall, and is built and maintained by one person. If the record here is useful to you, a few dollars keeps it going.

Processed by Stripe in a separate window. LegiList never sees card details. Other amounts

From Indiana's official records (iga.in.gov), checked Nov 14, 2026. Text links go to the official versions; LegiList does not copy bill text.