California · Assembly Bill 2111 · 2025-2026 Regular Session

Electricity: transmission planning and transmission facilities.

  1. Introduced Feb 18, 2026
  2. In committee Mar 9, 2026
  3. Passed the Assembly May 21, 2026
  4. Passed the Senate Aug 25, 2026
  5. To the governor Sep 3, 2026
  6. Became law Sep 20, 2026

What it does

The legislature's own summary of the bill, or its official long title.

(1)Existing law requires the Public Utilities Commission (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), to provide transmission-focused guidance to the Independent System Operator (ISO) about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on…

Read the full title (608 words)

(1)Existing law requires the Public Utilities Commission (PUC), in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission), to provide transmission-focused guidance to the Independent System Operator (ISO) about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the ISO to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified. On December 23, 2022, the PUC, the Energy Commission, and the ISO entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure. Existing law requires the Energy Commission and the PUC, in coordination with the ISO, every 5 years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the state’s energy goals. This bill would require those entities, on or before January 1, 2028, to update the memorandum and workplan to, among other things, ensure that the memorandum and workplan reflect the requirements of Federal Energy Regulatory Commission Order 1920, as applicable. (2)Existing law vests the PUC with regulatory authority over public utilities, including electrical corporations. Existing law requires the PUC to identify a diverse and balanced portfolio of resources needed to ensure a reliable electricity supply that provides optimal integration of renewable energy and resource diversity in a cost-effective manner, as specified. This bill would require that the portfolio provide optimal integration in a cost-effective and risk-prudent manner, as specified. (3)Existing law requires that the above-described transmission-focused guidance provided to the ISO provide projections each year to support planning and approvals by the ISO in its annual transmission planning process, including projections of resource portfolios and electricity demand by region for at least 15 years into the future, as specified. Existing law expresses the state policy that planning for new transmission facilities include consideration of the goal of increasing systemwide reliability and cost efficiency, among other state policy goals. This bill would require that the transmission-focused guidance takes into account uncertainty and optionality, is risk prudent, and supports compliance with Federal Energy Regulatory Commission orders, as specified. The bill would remove the requirement that the projections be provided annually and would require the projections of resource portfolios and electricity demand by region to be for at least 20, rather than 15, years into the future. The bill would add to those state policy goals reducing resource interconnection timelines and supporting achievement of the state’s energy, climate change, and air quality goals. (4)This bill would incorporate additional changes to Section 454.57 of the Public Utilities Code proposed by AB 2369 to be operative only if this bill and AB 2369 are enacted and this bill is enacted last. (5)Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime. Because certain provisions of this bill would be a part of the act and because a violation of a PUC action implementing its requirements would be a crime, the bill would impose a state-mandated local program by creating a new crime. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.

Every action

31 steps, oldest first, as the legislature records them.

Show the 23 earlier steps
  1. AssemblyRead first time. To print.
  2. AssemblyFrom printer. May be heard in committee March 21.
  3. CommitteeReferred to Com. on U. & E. · Assembly Utilities and Energy
  4. CommitteeFrom committee chair, with author's amendments: Amend, and re-refer to Com. on U. & E. Read second time and amended. · Assembly Utilities and Energy
  5. CommitteeRe-referred to Com. on U. & E. · Assembly Utilities and Energy
  6. CommitteeFrom committee chair, with author's amendments: Amend, and re-refer to Com. on U. & E. Read second time and amended. · Assembly Utilities and Energy
  7. CommitteeRe-referred to Com. on U. & E. · Assembly Utilities and Energy
  8. CommitteeFrom committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 17. Noes 0.) (April 8). · Assembly Utilities and Energy
  9. AssemblyRead second time and amended.
  10. CommitteeRe-referred to Com. on APPR. · Assembly Appropriations
  11. CommitteeIn committee: Set, first hearing. Referred to APPR. suspense file. · Assembly Appropriations
  12. CommitteeFrom committee: Do pass. (Ayes 11. Noes 0.) (May 14). · Assembly Appropriations
  13. AssemblyRead second time. Ordered to third reading.
  14. AssemblyRead third time. Passed. Ordered to the Senate. (Ayes 71. Noes 0. Page 5221.)
  15. SenateIn Senate. Read first time. To Com. on RLS. for assignment.
  16. CommitteeReferred to Com. on E., U & C. · Senate Energy, Utilities and Communications
  17. CommitteeFrom committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on E., U & C. · Senate Energy, Utilities and Communications
  18. CommitteeFrom committee: Do pass and re-refer to Com. on APPR. (Ayes 17. Noes 0.) (June 16). Re-referred to Com. on APPR. · Senate Energy, Utilities and Communications
  19. CommitteeIn committee: Set, first hearing. Hearing canceled at the request of author. · Senate Appropriations
  20. CommitteeFrom committee chair, with author's amendments: Amend, and re-refer to committee. Read second time, amended, and re-referred to Com. on APPR. · Senate Appropriations
  21. CommitteeIn committee: Referred to APPR. suspense file. · Senate Appropriations
  22. CommitteeFrom committee: Do pass. (Ayes 7. Noes 0.) (August 13). · Senate Appropriations
  23. SenateRead second time. Ordered to third reading.
  1. SenateRead third time and amended. Ordered to second reading.
  2. SenateRead second time. Ordered to third reading.
  3. SenateRead third time. Passed. Ordered to the Assembly. (Ayes 40. Noes 0. Page 5805.).
  4. AssemblyIn Assembly. Concurrence in Senate amendments pending.
  5. AssemblySenate amendments concurred in. To Engrossing and Enrolling. (Ayes 79. Noes 0. Page 6600.).
  6. GovernorEnrolled and presented to the Governor at 4 p.m.
  7. GovernorApproved by the Governor.
  8. Secretary of StateChaptered by Secretary of State - Chapter 382, Statutes of 2026.

Roll calls

8 recorded votes: 3 on the floor, 5 in committee. Each shows how every member voted.

AB 2111 Papan Assembly Third Reading · Full Assembly

Passed 71–0
May 21, 2026 · journal entry
Yes 71 No 0 Not voting 9
Democrats: 56 yes, 0 no Republicans: 15 yes, 0 no
How each member voted

Yes · 71

Not voting · 9

Assembly 3rd Reading AB2111 Papan et al. By McNerney · Full Senate

Passed 40–0
Aug 25, 2026 · journal entry
Yes 40 No 0
Democrats: 30 yes, 0 no Republicans: 10 yes, 0 no
How each member voted

Yes · 40

AB 2111 Papan Concurrence in Senate Amendments · Full Assembly

Passed 79–0
Aug 26, 2026 · journal entry
Yes 79 No 0
Democrats: 60 yes, 0 no Republicans: 19 yes, 0 no
How each member voted

Yes · 79

Committee and other votes

DateWhereQuestionResult
Apr 8, 2026 Assembly Utilities and Energy Do pass as amended and be re-referred to the Committee on [Appropriations]
Members

Yes · 17

Not voting · 1

Passed 17–0
May 14, 2026 Assembly Appropriations Do pass.
Members

Yes · 11

Not voting · 4

Passed 11–0
Jun 16, 2026 Senate Energy, Utilities and Communications Do pass, but first be re-referred to the Committee on [Appropriations]
Members

Yes · 17

Passed 17–0
Aug 3, 2026 Senate Appropriations Placed on suspense file
Members

Yes · 7

Passed 7–0
Aug 13, 2026 Senate Appropriations Do pass
Members

Yes · 7

Passed 7–0

Sponsors

The member who introduced it, joined by 1 cosponsor: 1 Democrat.

All 1 cosponsor

Support LegiList

This page is free, carries no paywall, and is built and maintained by one person. If the record here is useful to you, a few dollars keeps it going.

Processed by Stripe in a separate window. LegiList never sees card details. Other amounts

From California's official records (downloads.leginfo.legislature.ca.gov), checked Nov 18, 2026. Text links go to the official versions; LegiList does not copy bill text.