1st Quarter - Report

O'CONNELL & DEMPSEY, LLC for RIVERSIDE CO. FLOOD CONTROL & WATER CONSERVATION DISTRICT

Firm
Client
Income
$40,000
Expenses
—

What was lobbied

3 issue areas, each in the filer's own words, with who lobbied on it and where.

Budget/Appropriations BUD

Federal funding related to Corps projects in Infrastructure Investment and Jobs Act, P.L.117-58 Federal funding related to Corps projects including Murrieta Creek and the Santa Ana Levees project in the FY 2023 Energy and Water Development Appropriations Bill, H.R. 8255; and the Consolidated Appropriations Act, 2023, P.L.117-328, and the Corps of Engineers FY 2023 Work Plan Federal funding related to Corps of Engineers projects, including the Murrieta Creek Flood Protection project in the House FY 2024 Energy and Water Development Appropriations Bill, H.R.4394, and the Senate Energy and Water Development Appropriations Bill, S.2443, and the Corps FY 2024 Work Plan Federal authorization of a permanent easement to Riverside County across USDA lands in the House and Senate Interior, Environment and Related Agencies Appropriations Bills of FY2025 (bill numbers not yet available) Committee Report language regarding the reinstallation of a mural on a Corps of Engineers' Project in the House Energy and Water Development Appropriations Bill of FY2025 (bill number not yet available)

LobbyistCovered position, as disclosed
MIA O'CONNELL —

Contacted: Office of Management & Budget (OMB); SENATE; Agriculture, Dept of (USDA); HOUSE OF REPRESENTATIVES; Army, Dept of (Corps of Engineers)

Bills named: S. 2443 (118th), H.R. 4394 (118th), H.R. 8255 (118th)

Natural Resources NAT

Corps of Engineers flood protection and ecosystem restoration project implementation and project approvals, including the Murrieta Creek Flood Protection Project; and monitoring construction management and development of an Economic Re-evaluation Report for the Murrieta Creek Flood Protection project (generally, no specific legislation), and implementation of the Corps' P.L. 84-99 Emergency Authority Project, the Santa Ana Levees Discussions regarding possible funding and approval of easement by USDA Forest Service for the Cactus Channel Project

LobbyistCovered position, as disclosed
MIA O'CONNELL —

Contacted: Army, Dept of (Corps of Engineers); SENATE; Agriculture, Dept of (USDA); Office of Management & Budget (OMB); HOUSE OF REPRESENTATIVES

Urban Development/Municipalities URB

Corps of Engineers flood protection and ecosystem restoration project implementation for the Murrieta Creek Flood Protection Project, and project approvals; and monitoring construction management and development of an Economic Re-evaluation Report for the Murrieta Creek Flood Protection Project (generally, no specific legislation), and implementation of the Corps' P.L. 84-99, Emergency Authority Project, the Santa Ana Levees Discussions regarding possible funding and approval of easement by USDA Forest Service for the Cactus Channel Project

LobbyistCovered position, as disclosed
MIA O'CONNELL —

Contacted: Office of Management & Budget (OMB); SENATE; HOUSE OF REPRESENTATIVES; Army, Dept of (Corps of Engineers)

Support LegiList

This page is free, carries no paywall, and is built and maintained by one person. If the record here is useful to you, a few dollars keeps it going.

Processed by Stripe in a separate window. LegiList never sees card details. Other amounts

Shown as published by the Senate Office of Public Records and the House Clerk under the Lobbying Disclosure Act. The official filing is the record; open it for the full form.