S 2314 · 113th Congress 2013–2015, ended

Removing Repeated Executive Delays to Transboundary Approvals of Pipelines and Engineering Act

Fact sheet

Latest action · May 8, 2014 Read twice and referred to the Committee on Homeland Security and Governmental Affairs.

Progress

Where this bill reached, and when. A stage with no date was not reached; one that failed a vote and later carried shows the date it carried.

  1. IntroducedMay 8, 2014
  2. Passed SenateNot reached
  3. Passed HouseNot reached
  4. To the PresidentNot reached
  5. Became lawNot reached

Summary

Removing Repeated Executive Delays to Transboundary Approvals of Pipelines and Engineering Act - Designates and empowers the Secretary of State to receive all applications (except those received by the Secretary of Energy [DOE] under current law) for permits for the construction, connection, operation, or maintenance, at the U.S. borders, of facilities for the exportation or importation to or from a foreign country of petroleum, petroleum products, coal, other fuels, certain products, water or sewage, as well as persons or things.

Prescribes requirements and procedures for granting a permit.

Authorizes TransCanada Keystone Pipeline, L.P. to construct, connect, operate, and maintain the pipeline and cross-border facilities specified in an application filed by TransCanada Corporation to the Department of State on May 4, 2012.

Deems the Final Supplemental Environmental Impact Statement regarding the pipeline issued by the Secretary of State in January 2014 to fully satisfy the National Environmental Policy Act of 1969, and any law that requires federal agency consultation or review, including the Endangered Species Act of 1973.

Restricts any legal challenges regarding a federal agency action and such facilities to judicial review on direct appeal to the U.S. Court of Appeals for the District of Columbia Circuit.

Directs the Comptroller General (GAO) to review any Executive order issued by the President that is not based on the President's exclusive constitutional authority.

Cosponsors

Members who signed on, in the order they did.

No cosponsors are on file for this measure.

Actions 2

Everything that happened, newest first.

  1. May 8, 2014Introduced in Senate
  2. May 8, 2014Read twice and referred to the Committee on Homeland Security and Governmental Affairs.

Related bills 3

Companion bills and other measures the record links to this one.

BillTitleRelationshipLatest action
S 2280A bill to approve the Keystone XL Pipeline.Related billNov 18, 2014
S 2554Keystone XL Pipeline Approval ActRelated billOct 1, 2014
HR 5682To approve the Keystone XL Pipeline.Related billNov 17, 2014

Subjects

Assigned by the Library of Congress. Policy area: Energy.

Text 1

Each version as it was printed, newest first.

  1. May 8, 2014Introduced in Senate

Support LegiList

This page is free, carries no paywall, and is built and maintained by one person. If the record here is useful to you, a few dollars keeps it going.

Processed by Stripe in a separate window. LegiList never sees card details.

Everything here is as published by Congress: the summary is the Congressional Research Service's, the action wording is the clerks', and the subjects are the Library of Congress's. How far it got is read from the actions themselves, taking the most recent one of each kind, so a bill that failed a vote and later passed is shown as having passed. Records come from this bill on Congress.gov and govinfo.gov.